Morray Firth Crossing
The installation of an 11” Gas Pipeline (1,400 m.) across the Morray Firth Crossing in Scotland.
A range of marine and onshore equipment was assigned to this project, such as:
- Survey Vessels
- Backhoe Dredgers
- Split Hopper Barges
- Assistance Tugs
- Leveling / Ploughing Equipment
- Pulling Winches
- All sorts of land based equipment
The main activities for the project included:
- Installing engineering of crossing
- Pipe stringing
- Crossing dredging & excavation works
- Pull wire installation & pull
- Crossing backfilling works
- Crossing protection by means of rock placement